Find out the executed versus...
How can we help you?
Find out the progress made versus the programmed progress of the main works in Bogota and the Region
The portfolio includes 79 contracts with a total value of $63.62 trillion and a physical completion rate of 28.0% compared to the scheduled 30.2%, representing a negative variance of –2.25%. The total executed amounts to $17.80 trillion. For the 35 contracts currently under construction, physical progress stands at 54.9% compared to the scheduled 58.9%, with a deviation of –4.03% and a cumulative executed amount of $17.26 trillion.
The progress by project is presented below:
Bogotá Metro Line 1: Progress stands at 73.75% compared to the scheduled 77.03%, with a negative deviation of –3.28%, classified as a yellow traffic light. The total executed amount is $12.61 trillion, and construction is scheduled to be completed in September 2027, with operations set to begin in March 2028.
Regiotram de Occidente: Progress stands at 13.29% compared to the scheduled 20.88%, with a negative deviation of –7.59%, classified as a red light. The total amount spent is $494.18 billion. Construction is scheduled to be completed in January 2030, with operations set to begin in July 2030.
Transmilenio along Av. 68: Overall progress stands at 71.08% compared to the scheduled 76.85%, with a negative deviation of –5.76%, classified as a red light. The total amount spent amounts to $1.95 trillion, and construction is scheduled to be completed in October 2032. The sections with the greatest delays are Section 6 (–20.39%), Section 3 (–10.17%), Section 2 (–8.66%), and Section 7 (–7.20%). Section 1 is slightly ahead of schedule at +0.98%.
Transmilenio along Ciudad de Cali Avenue: Progress stands at 76.41% compared to the scheduled 87.90%, with a negative deviation of –11.48%, classified as a red light. The total amount spent amounts to $541.91 billion, and construction is scheduled to be completed in December 2030. Group 2 (IDU-1647-2020) is the furthest behind, at 58.22% compared to the expected 91.94% (–33.72%), in an expired status.
Transmilenio Soacha Phases II and III: Consolidated progress stands at 74.32% compared to the scheduled 74.24%, with a positive deviation of +0.08%, classified as green. Lot 2 (TS02) is 100% complete compared to the scheduled 100%, and Lot 1 (TS01) is 56.92% complete compared to the scheduled 56.79% (+0.13%, green light). The total amount executed amounts to $368.86 billion, and the service level guarantee is scheduled to end in September 2031.
Improvement Projects — Sidewalks, bike paths, pedestrian bridges, and greenways: Overall progress stands at 46.64% compared to the scheduled 56.59%, representing a negative deviation of –9.95%, classified as a red light. The total amount executed amounts to $176.25 billion out of a contract value of $377.86 billion. The contracts with the greatest delays are the 112th Street Pedestrian Bridge at Carrera 9 (IDU-215-2020, expired, –63.59%), Sidewalks and bike paths on 92nd and 94th Streets from Carrera 7 7 to Autopista Norte (IDU-2400-2024, –69.01%) and Sidewalks and Bike Lanes on Calle 116 between Cra. 9 and Av. Boyacá (IDU-1279-2020, –71.79%). The contracts for Road Construction and EP Montevideo and Puente Aranda — Group 2 (IDU-1752-2021) and Road Construction and EP Montevideo and Puente Aranda — Group 3 (IDU-1839-2021) show progress of +2.06% and +2.50%, respectively. Construction for the group is scheduled to be completed in May 2027.
Laureano Gómez Ave. (AK 9) between AC 170 and AC 193: Progress stands at 99.86% compared to the scheduled 99.86%, with a deviation of 0.00%, classified as green. The total amount spent amounts to $145.90 billion, and construction is scheduled to be completed in May 2026.
Calle 13: Progress stands at 30.04% compared to the 29.83% scheduled for Lot 1 — Puente Aranda Overpass, with a positive deviation of +0.21%, classified as green. The total amount spent is $143.54 billion, and construction is scheduled to be completed in January 2028.
Carrera Séptima Green Corridor: With a consolidated progress rate of 6.05% compared to the scheduled 6.21% across the three active contracts, it shows a negative deviation of –0.16%, classified as a yellow light. The total amount executed amounts to $87.86 billion, and construction is scheduled to be completed in March 2032. The deviations by section are: Carrera Séptima Green Corridor — Calle 127 to Calle 183 (IDU-1727-2023, –0.21%), Carrera Séptima — Calle 183 to Calle 200 (IDU-1740-2023, –0.21%) and Green Corridor Cra. Séptima — Calle 99 to Calle 127 (IDU-1739-2023, –0.06%).
Alameda Medio Milenio Cycle: Shows 0.58% progress compared to the scheduled 81.15%, with a negative deviation of –80.57%, classified as a red light. The project is currently suspended (IDU-1177-2023). The total amount executed amounts to $510.39 million, and construction was scheduled to be completed in June 2026.
Note 1: The $63.62 trillion corresponds exclusively to the sum of the present value of the construction contracts signed, in all their statuses under supervision (In Progress, Completed, Suspended, and Expired).
Note 2: The amount of $31.47 billion corresponds to the sum of the current value of the work under the 35 contracts in the construction and pre-construction stages with statuses of in progress, suspended, and expired, excluding completed contracts, the value of audits, and the value of contracts yet to be awarded.
Description
Monitoring Methodology
The Bogotá Chamber of Commerce monitors 29 mobility infrastructure projects in Bogotá and the surrounding region, which involve 79 contracts across various categories: studies and designs, feasibility, pre-feasibility, pre-construction, and construction.
The “Percentage Completed” indicator reflects the physical progress of the contracts. The “Total Completed” corresponds to the sum of the product of the percentage completed and the respective current value of each contract. The schedule variance corresponds to the difference between the percentage completed and the scheduled percentage: if the difference is negative, the project is behind schedule; if it is positive, the project is ahead of schedule.
Recommendations for using the dashboard: When you hover the cursor over the graphs or tables, a box will appear with expanded information related to the highlighted area. Selecting or clicking on a project in the table will filter the specific fields in the graph, displaying data only for the selected project. Likewise, by clicking on a specific area of the graphs, you can view the list of projects corresponding to the selected data in the table. In the project table, you can scroll down to view all listed projects.
