The construction of the Bogota Metro...
How can we help you?
See here the impact of infrastructure projects on job creation in Bogotá and the surrounding region
Analysis of Direct Job Creation.
As of September 27, 2026, the portfolio shows a total of 29,046 direct jobs created across 30 contracts, of which 27,875 are for construction work and 1,171 are for supervision. The report includes only contracts with the status “In Progress” or “Suspended” that are in the construction phase. Among these is the 112th Street and Carrera 9 Pedestrian Bridge (VA23), which accounts for 102 jobs (70 in construction + 32 in supervision). Breakdown by Contracting Entity
The EMB accounts for the largest number with 15,015 jobs (51.69%). The IDU accounts for 9,215 jobs (31.73%). The EFR accounts for 3,989 jobs (13.73%). The ANI reports 827 jobs (2.85%).
By project, the Bogotá Metro’s First Line accounts for the largest number of jobs, with 15,015 (14,851 construction jobs + 164 supervision jobs—a figure confirmed by the EMB in official letter PQRSD-S26-01239 dated September 17, 2026), followed by TransMilenio on Av. 68 with 5,065 consolidated jobs (4,724 + 341, across all 9 sections), TransMilenio Phases II and III in Soacha with 2,239 consolidated jobs (2,180 + 59, across both lots), Regiotram de Occidente with 1,750 jobs (1,661 + 89), Calle 13 (Lot 1) with 1,104 jobs (1,034 + 70), and Ciclo Alameda Medio Milenio with 1,087 jobs (1,056 + 31). Next are the Urban Renewal Projects with 799 jobs (625 + 174), the Carrera Séptima Green Corridor with 689 jobs (503 + 186), the Troncal de los Andes with 515 jobs, the TransMilenio Troncal on Av. Ciudad de Cali with 471 jobs (414 + 57), the ALO Southern Section with 160 jobs, and the Northern Access Roads Phase 2 with 152 jobs.
Note 1: The employment data reported in this report comes from sources with different update dates. The report’s cutoff date is September 27, 2026, but that is not the actual date for each data point: each figure retains the update date from its source, as indicated below.
IDU. The information comes from the Project Viewer records, accessed on September 14, 2026. That is the date on which most of the records were accessed and updated. The following records have a different update date:
New Suba–Cota Road (contract IDU-1815-2021): August 31, 2026.
Carrera Séptima Green Corridor, Calle 127 to Calle 183 (contract IDU-1727-2023): August 31, 2026.
Cross-Connections at Calle 73, Calle 79B, and Calle 85 (contract IDU-1767-2023): September 6, 2026.
Alameda Medio Milenio Bike Path (contract IDU-1177-2023): September 7, 2026.
TransMilenio Trunk Line Av. 68, Section 3 (Contract IDU-347-2020): September 7, 2026.
EMB. Deadline: August 31, 2026 (Official Letter PQRSD-S26-01239 dated September 17, 2026).
EFR. Deadline: August 31, 2026 (email dated September 24, 2026).
ANI. The completion date varies by contract, according to the latest report available from SECOP: ALO Southern Section: completion in May 2026 (Monthly Supervisory Report No. 47—May 2026—Version 1—Approved, p. 165).
Northern Access Roads Phase II: as of June 30, 2026 (Supervisory Report No. 49, VEJ-506-2022, section 6.3.6, p. 107).
Andes Trunk Line: as of April 10, 2026 (Monthly Audit Report No. 109, ETSA-SIGA Consortium, Chapter 7.7.2.3.3, p. 1243).
Note 2: Employment data refer only to contracts with the status “In Progress” and “Suspended” during the Construction phase. Contracts with the status “Completed” and “Expired” are excluded, as are the study and design, feasibility, comprehensive evaluation, comprehensive structuring, and prequalification phases.
Description
The Bogotá Chamber of Commerce monitors 31 infrastructure projects for mobility in Bogotá and the surrounding region, which involve 81 contracts at various stages of implementation: studies and design, feasibility, pre-feasibility, pre-construction, and construction. Here you can track the progress of the projects and their impact on job creation.
The “Percentage Completed” indicator reflects the physical progress of the contracts. “Total Completed” corresponds to the sum of the product of the percentage completed and the respective current value of each contract. The schedule variance corresponds to the difference between the percentage completed and the scheduled percentage: if the difference is negative, the project is behind schedule; if it is positive, the project is ahead of schedule.
The traffic-light system established for monitoring assigns the color green (optimal) when the difference between the percentage completed and the percentage scheduled is greater than or equal to zero—that is, on schedule or ahead of schedule; yellow (warning delay) when the difference is negative up to −5 percentage points, in which case the contract is closely monitored; and red (critical delay) when the difference is less than −5 percentage points, a situation that requires a formal alert and urgent recommendations. When any of the necessary data is missing, the contract is classified as “Unclassifiable.”
For example, Transmilenio Soacha Phases II and III (−4.99 percentage points) is classified as yellow, and the Regiotram de Occidente (−18.99 percentage points) as red.
